Conversions from LT Single phase to 3 phase done in APSPDCL July-2021 To September-2021
# Sub-Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 RENIGUNTA 1 10.72 10.72 10.72 100.00
2 TIRUPATI CCO 12 5.04 68.24 16.66 91.67
3 TIRUPATI OPERATION1 11 0.37 39.96 10.6 90.91
4 TIRUPATI OPERATION2 18 2.59 68.26 28.26 61.11
Total 42 0.37 68.26 19.9 78.57