Conversions from LT Single phase to 3 phase done in APSPDCL Jan-2021 To Mar-2021
# Sub-Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 TIRUPATI CCO 1 14.26 14.26 14.26 100.00
2 TIRUPATI OPERATION2 1 15.56 15.56 15.56 100.00
Total 2 14.26 15.56 14.91 100.00