Conversions from LT Single phase to 3 phase done in APSPDCL April-2022 To June-2022
# Sub-Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 CHITTOOR RURAL-3 1 19.31 19.31 19.31 100.00
2 CHITTOOR TOWN 8 1.88 28.31 19.09 100.00
Total 9 1.88 28.31 19.12 100.00