Conversions from LT Single phase to 3 phase done in APSPDCL October-2022 To December-2022
# Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 KAVALI 1 13.21 13.21 13.21 100.00
2 NELLORE TOWN 11 7.2 35.78 14.7 90.91
Total 12 7.2 35.78 14.57 91.67