Conversions from LT Single phase to 3 phase done in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 NELLORE TOWN I 6 6.95 38.28 15.68 83.33
2 NELLORE TOWN II 10 10.43 28.48 19.88 100.00
Total 16 6.95 38.28 18.31 93.75