Conversions from LT Single phase to 3 phase done in APSPDCL October-2021 To December-2021
# Sub-Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 BUCHI 3 16.66 20.36 18.01 100.00
2 KOVUR 1 13.52 13.52 13.52 100.00
Total 4 13.52 20.36 16.89 100.00