Conversions from LT Single phase to 3 phase done in APSPDCL July-2021 To September-2021
# Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 ADONI 1 3.32 3.32 3.32 100.00
2 DHONE 1 7.13 7.13 7.13 100.00
3 KURNOOL 10 4.22 26.45 10.64 100.00
4 NANDYAL 11 1.64 39.53 7.55 90.91
Total 23 1.64 39.53 8.69 95.65