Conversions from LT Single phase to 3 phase done in APSPDCL April-2022 To June-2022
# Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 DHONE 1 27.17 27.17 27.17 100.00
2 KURNOOL 28 3.86 34.0 14.23 96.43
3 KURNOOL RURALS 4 5.65 12.06 7.6 100.00
4 NANDYAL 1 38.9 38.9 38.9 0.00
Total 34 3.86 38.9 14.56 94.12