Conversions from LT Single phase to 3 phase done in APSPDCL July-2021 To September-2021
# Sub-Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 NANDYAL 7 1.64 39.53 8.64 85.71
2 NANDYAL-CCO 4 4.05 6.52 5.64 100.00
Total 10 4.22 26.45 10.64 100.00