Conversions from LT Single phase to 3 phase done in APSPDCL July-2021 To September-2021
# Sub-Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 KODUR 1 2.01 2.01 2.01 100.00
2 RAJAMPET 2 18.05 31.05 24.55 50.00
Total 9 1.38 15.37 6.95 100.00