Conversions from LT Single phase to 3 phase done in APSPDCL Apr-2021 To Jun-2021
# Section Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 PRODDATUR EAST 1 32.76 32.76 32.76 0.00
2 PRODDATUR NORTH 2 0.77 18.76 9.77 100.00
3 PRODDATUR WEST 2 12.61 24.65 18.63 100.00
Total 5 0.77 32.76 17.91 80.00