Conversions from LT Single phase to 3 phase done in APSPDCL Apr-2021 To Jun-2021
# Section Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 C K DINNE 3 11.16 21.77 15.17 100.00