Conversions from LT Single phase to 3 phase done in APSPDCL October-2021 To December-2021
# Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 ANANTHAPUR 4 3.25 5.46 4.37 100.00
2 GOOTY 1 6.76 6.76 6.76 100.00
3 HINDUPUR 2 5.05 6.35 5.7 100.00
4 KADIRI 3 2.25 6.95 4.62 100.00
5 KALYANDURG 5 3.55 49.34 25.54 60.00
Total 15 2.25 49.34 11.81 86.67