Conversions from LT Single phase to 3 phase done in APSPDCL April-2022 To June-2022
# Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 ANANTHAPUR 1 0.9 0.9 0.9 100.00
2 HINDUPUR 1 8.94 8.94 8.94 100.00
3 KADIRI 2 0.77 14.84 7.8 100.00
Total 4 0.77 14.84 6.36 100.00