Conversions from LT Single phase to 3 phase done in APSPDCL Apr-2021 To Jun-2021
# Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 KADIRI 4 11.31 19.7 16.56 100.00
Total 4 11.31 19.7 16.56 100.00