Conversions from LT Single phase to 3 phase done in APSPDCL Apr-2020 To Sep-2020
# Sub-Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 KADIRI TOWN 1 2.86 2.86 2.86 100.00
2 PUTTAPARTHY 1 2.7 2.7 2.7 100.00
Total 1 12.65 12.65 12.65 100.00