Conversions from LT Single phase to 3 phase done in APSPDCL October-2021 To December-2021
# Sub-Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 ANANTHAPUR EAST 1 5.46 5.46 5.46 100.00
2 ANANTHAPUR TOWN 1 2 4.16 4.64 4.4 100.00
3 ANANTHAPUR TOWN 2 1 3.25 3.25 3.25 100.00
Total 4 3.25 5.46 4.37 100.00