Scheduled outage performance in APSPDCL April-2022 To June-2022
# Circle Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 ANANTHAPUR 864 213 651 75.35
2 KADAPA 1219 142 1077 88.35
3 KURNOOL 1829 143 1686 92.18
4 NELLORE 1069 67 1002 93.73
5 TIRUPATI 2300 336 1964 85.39
Total 7281 901 6380 87.63