Scheduled outage performance in APSPDCL July-2021 To September-2021
# Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 CHITTOOR RURALS 352 15 337 95.74
2 CHITTOOR TOWN 253 8 245 96.84
3 MADANAPALE 173 26 147 84.97
4 PILERU 150 9 141 94.00
5 PUTTUR 517 8 509 98.45
6 TIRUPATI RURALS 415 7 408 98.31
7 TIRUPATI TOWN 118 1 117 99.15
Total 1978 74 1904 96.26