Scheduled outage performance in APSPDCL October-2021 To December-2021
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 RENIGUNTA 44 0 44 100.00
2 TIRUPATI CCO 19 0 19 100.00
3 TIRUPATI OPERATION1 14 0 14 100.00
4 TIRUPATI OPERATION2 14 2 12 85.71
Total 91 2 89 97.80