Scheduled outage performance in APSPDCL July-2022 To September-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 OPN SUBSTATION-TPT 13 0 13 100.00
2 TIRUCHANUR CCO 16 0 16 100.00
3 TIRUPATI RURALS II 6 0 6 100.00
4 TIRUPATI SOUTH 4 0 4 100.00
Total 39 0 39 100.00