Scheduled outage performance in APSPDCL April-2022 To June-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 RENIGUNTA OPERATION 8 0 8 100.00
2 RENIGUNTA RURALS 32 9 23 71.88
Total 40 9 31 77.50