Scheduled outage performance in APSPDCL Apr-2021 To Jun-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 DHAMINEDU 5 0 5 100.00
2 KORLAGUNTA 2 0 2 100.00
3 MANGALAM 3 1 2 66.67
4 MANGALAM RURALS 4 0 4 100.00
5 TIRUPATI EAST 5 0 5 100.00
Total 19 1 18 94.74