Scheduled outage performance in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 RENIGUNTA 43 0 43 100.00
2 TIRUPATI CCO 21 5 16 76.19
3 TIRUPATI OPERATION1 4 0 4 100.00
4 TIRUPATI OPERATION2 19 1 18 94.74
Total 87 6 81 93.10