Scheduled outage performance in APSPDCL Apr-2020 To Sep-2020
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 RENIGUNTA OPERATION 9 0 9 100.00
2 RENIGUNTA RURALS 46 1 45 97.83
Total 55 1 54 98.18