Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 K.V.B. PURAM 28 0 28 100.00
2 PAPANAIDUPETA 8 0 8 100.00
3 RURAL SRIKALAHASTHI 54 3 51 94.44
4 YERPEDU OPERATION 40 2 38 95.00
Total 130 5 125 96.15