Scheduled outage performance in APSPDCL January-2022 To March-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 K.V.B. PURAM 32 4 28 87.50
2 PAPANAIDUPETA 17 0 17 100.00
3 RURAL SRIKALAHASTHI 69 0 69 100.00
4 YERPEDU OPERATION 56 0 56 100.00
Total 174 4 170 97.70