Scheduled outage performance in APSPDCL January-2022 To March-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 CHANDRAGIRI OPERATION 30 0 30 100.00
2 CHANDRAGIRI RURAL 43 0 43 100.00
3 TIRUPATI RURAL 32 0 32 100.00
Total 105 0 105 100.00