Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 KARVETI NAGARAM 63 4 59 93.65
2 S.R.R.PURAM 14 2 12 85.71
3 VEDURUKUPPAM 40 6 34 85.00
Total 117 12 105 89.74