Scheduled outage performance in APSPDCL July-2022 To September-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 NAGARI OPERATION 42 1 41 97.62
2 NAGARI RURAL 28 0 28 100.00
3 NINDRA 40 0 40 100.00
4 PANNUR 60 6 54 90.00
Total 170 7 163 95.88