Scheduled outage performance in APSPDCL April-2022 To June-2022
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 KARVETINAGAR CCO 54 7 47 87.04
2 NAGALAPURAM OPERATION 97 7 90 92.78
3 NAGARI 165 1 164 99.39
4 PUTTUR OPERATION 118 1 117 99.15
Total 434 16 418 96.31