Scheduled outage performance in APSPDCL Apr-2020 To Sep-2020
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 NAGARI OPERATION 32 3 29 90.63
2 NAGARI RURAL 47 5 42 89.36
3 NINDRA 86 0 86 100.00
4 PANNUR 86 2 84 97.67
Total 251 10 241 96.02