Scheduled outage performance in APSPDCL October-2022 To December-2022
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 MADANAPALLI OPERATION 92 10 82 89.13
2 MULAKALACHERVU 89 3 86 96.63
3 RURAL-MADANAPALLI 62 9 53 85.48
Total 243 22 221 90.95