Scheduled outage performance in APSPDCL July-2021 To September-2021
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 MADANAPALLI OPERATION 37 3 34 91.89
2 MULAKALACHERVU 42 2 40 95.24
3 PUNGANUR CCO 58 20 38 65.52
4 RURAL-MADANAPALLI 36 1 35 97.22
Total 173 26 147 84.97