Scheduled outage performance in APSPDCL Jan-2021 To Mar-2021
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 MADANAPALLI OPERATION 20 2 18 90.00
2 MULAKALACHERVU 85 5 80 94.12
3 PUNGANUR CCO 123 1 122 99.19
4 RURAL-MADANAPALLI 46 2 44 95.65
Total 274 10 264 96.35