Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 GREAMSPET WEST 15 0 15 100.00
2 KONGAREDDI PALLI 8 0 8 100.00
3 MITTOOR NORTH 5 0 5 100.00
4 SANTHAPETA SOUTH 9 0 9 100.00
Total 37 0 37 100.00