Scheduled outage performance in APSPDCL April-2022 To June-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 AVALKONDA 54 14 40 74.07
2 GANGADHARA NELLORE 28 6 22 78.57
3 PALASAMUDRAM 45 18 27 60.00
4 PENUMUR 64 5 59 92.19
5 PUTHALAPATTU 61 10 51 83.61
Total 252 53 199 78.97