Scheduled outage performance in APSPDCL Apr-2020 To Sep-2020
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 CHITTOOR CCO 238 11 227 95.38
2 CHITTOOR OPERATION 77 0 77 100.00
3 CHITTOOR RURAL-III 121 3 118 97.52
Total 436 14 422 96.79