Scheduled outage performance in APSPDCL Apr-2021 To Jun-2021
# Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 ATMAKURU 35 2 33 94.29
2 GUDUR 128 3 125 97.66
3 KAVALI 119 1 118 99.16
4 NAIDUPETA 99 3 96 96.97
5 NELLORE RURALS 100 3 97 97.00
6 NELLORE TOWN 13 0 13 100.00
Total 494 12 482 97.57