Scheduled outage performance in APSPDCL October-2022 To December-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 MUTHUKURU 7 0 7 100.00
2 NARAYANA REDDY PETA 8 3 5 62.50
3 NLR RUR-2 6 0 6 100.00
4 NLR RUR-3 6 2 4 66.67
5 VENKATACHALAM C-O 1 0 1 100.00
Total 28 5 23 82.14