Scheduled outage performance in APSPDCL October-2022 To December-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 KODUR 61 2 59 96.72
2 KOTHURU 60 0 60 100.00
3 MUDIVARTHYPALEM 22 1 21 95.45
4 MYPADU 61 0 61 100.00
5 T.P.GUDUR 25 0 25 100.00
Total 229 3 226 98.69