Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 CHEJERLA 5 1 4 80.00
2 PODALAKUR 13 5 8 61.54
3 VIRUVUR 5 1 4 80.00
Total 58 12 46 79.31