Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 BALAYAPALLI 18 3 15 83.33
2 DAKKILI 19 0 19 100.00
3 VENKATAGIRI RURALS 38 4 34 89.47
4 VENKATAGIRI TOWN 2 0 2 100.00
Total 46 2 44 95.65