Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 NAIDUPETA RURALS 11 2 9 81.82
2 NAIDUPETA TOWN 7 0 7 100.00
3 OZILI 9 0 9 100.00
4 PELLAKUR 19 0 19 100.00
Total 46 2 44 95.65