Scheduled outage performance in APSPDCL October-2022 To December-2022
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 INAMADUGU 15 0 15 100.00
2 KOVUR RURALS 10 0 10 100.00
3 KOVUR TOWN 8 0 8 100.00
Total 70 0 70 100.00