Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 ALLURU RURALS 21 1 20 95.24
2 ALLURU-NRP 14 2 12 85.71
3 N.R.PALEM 20 5 15 75.00
4 UTUKUR 22 11 11 50.00
5 VIDAVALUR 25 10 15 60.00
Total 97 24 73 75.26