Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 INAMADUGU 7 6 1 14.29
2 KOVUR RURALS 6 4 2 33.33
3 KOVUR TOWN 4 1 3 75.00
Total 97 24 73 75.26