Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 CHENDODU 10 0 10 100.00
2 CHITTAMURU 7 1 6 85.71
3 KOTA 18 2 16 88.89
4 VAKADU 10 6 4 40.00
Total 33 2 31 93.94