Scheduled outage performance in APSPDCL October-2021 To December-2021
# Section Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 ALLAGADDA 80 0 80 100.00
2 CHAGALAMARRY 68 0 68 100.00
3 GOSPADU 31 0 31 100.00
4 RUDRAVARAM 93 0 93 100.00
5 SIRIVELLA 43 0 43 100.00
6 UYYALAWADA 18 0 18 100.00
Total 333 0 333 100.00