Scheduled outage performance in APSPDCL October-2021 To December-2021
# Sub-Division Number of Outages Number of times when supply was restored after 6pm Number of times when supply was restored before 6pm Percentage of Restorations before 6pm
1 ALLAGADDA 333 0 333 100.00
2 KOILKUNTLA 54 2 52 96.30
3 NANDYAL 83 0 83 100.00
4 NANDYAL-CCO 186 1 185 99.46
Total 195 4 191 97.95